Rhigos 400kV: grid connection queue
Rhigos 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
3 projects with 1,081 MW are waiting to connect here (largest by capacity: solar + storage, onshore wind). Contracted dates run from 13 Dec 2030 to 15 Oct 2037.
3projects in the queue
1,081 MWwaiting to connect
527 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
331 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Tarenni | TARENNI ENERGY PARK LIMITED | Onshore wind | 188 | 13 Dec 2030 | High | 29 Oct 2032 | Scoping | 1 |
| Nant Aman | NANT AMAN ENERGY PARK LIMITED | Onshore wind | 143 | 13 Dec 2030 | High | 29 Oct 2032 | Scoping | 1 |
| East Pit | CS UK HOLDINGS III LIMITED | Solar + storage | 750 | 15 Oct 2037 | Low | 15 Oct 2037 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Rhigos 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Rhigos B 400kV: 221 MW waiting
- Hirwaun: 120 MW waiting
- Cilfynydd 400kV: 2,998 MW waiting
- South Wales East Node A 275kV: 699 MW waiting
- Margam B 400kV: 350 MW waiting