Margam B 400kV: grid connection queue
Margam B 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 350 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 10 May 2037 to 10 May 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Caegarw Farm | Downing Renewable Developments LLP | Solar + storage | 350 | 10 May 2037 | Low | 10 May 2037 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 13 Oct 2026 | Caegarw Farm | 10 Mar 2037 | 10 May 2037 | +2 months |
Thinking of connecting near Margam B 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Margam 275kV: 151 MW waiting
- Hirwaun: 120 MW waiting
- Rhigos 400kV: 1,081 MW waiting
- Rhigos B 400kV: 221 MW waiting
- South Wales West Connection Node C 400kV: 288 MW waiting