South Wales West Connection Node C 400kV: grid connection queue

South Wales West Connection Node C 400kV · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

2 projects with 288 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 31 Dec 2037 to 31 Oct 2038.

2projects in the queue
288 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
2date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
NatPower Llanteg Green Energy ParkNP SPV 30 LIMITEDBattery storage4831 Dec 2037Low31 Dec 2037Scoping1
Lightsource Ferryside PVLightsource Renewable UK Development LimitedSolar + storage24031 Oct 2038Low31 Oct 2038Scoping1

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 2 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
13 Oct 2026NatPower Llanteg Green Energy Park31 Oct 202831 Dec 2037+110 months
13 Oct 2026Lightsource Ferryside PV30 Oct 203730 Oct 2038+12 months

Thinking of connecting near South Wales West Connection Node C 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.