South Wales West Connection Node C 400kV: grid connection queue
South Wales West Connection Node C 400kV · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 288 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 31 Dec 2037 to 31 Oct 2038.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| NatPower Llanteg Green Energy Park | NP SPV 30 LIMITED | Battery storage | 48 | 31 Dec 2037 | Low | 31 Dec 2037 | Scoping | 1 |
| Lightsource Ferryside PV | Lightsource Renewable UK Development Limited | Solar + storage | 240 | 31 Oct 2038 | Low | 31 Oct 2038 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 2 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 13 Oct 2026 | NatPower Llanteg Green Energy Park | 31 Oct 2028 | 31 Dec 2037 | +110 months |
| 13 Oct 2026 | Lightsource Ferryside PV | 30 Oct 2037 | 30 Oct 2038 | +12 months |
Thinking of connecting near South Wales West Connection Node C 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- SOUTH WALES WEST CONNECTION NODE A 132KV: 150 MW waiting
- Pont Abraham: 1,241 MW waiting
- Pont Abraham 132KV: 253 MW waiting
- South Wales West Connection Node B 400kV: 700 MW waiting
- South Wales West Connection Node A 400kV: 1,825 MW waiting