Pont Abraham: grid connection queue

Pont Abraham GSP · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

8 projects with 1,241 MW are waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Oct 2026 to 31 Oct 2028.

8projects in the queue
1,241 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
844 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Garreg Fawr Energy ParkGARREG FAWR ENERGY PARK LIMITEDOnshore wind19031 Oct 2026n/aScopingnone
Builth WellsABEREDW ENERGY PARK LIMITEDOnshore wind13331 Oct 2026n/aScopingnone
Bryn Gilwern Energy ParkBRYN GILWERN ENERGY PARK LIMITEDOnshore wind7531 Oct 2026n/aScopingnone
Nant Ceiment Energy ParkNANT CEIMENT ENERGY PARK LIMITEDOnshore wind8811 Sep 2027High8 Nov 2029Scopingnone
Lan Fawr Energy ParkLAN FAWR ENERGY PARK LIMITEDOnshore wind24611 Sep 2028High9 Nov 2030Scopingnone
BrynGwyn Energy ParkBRYNGWYN ENERGY PARK LIMITEDOnshore wind25031 Oct 2028High29 Dec 2030Scoping1
BlaenCothi Energy ParkBLAENCOTHI ENERGY PARK LIMITEDOnshore wind14531 Oct 2028High29 Dec 2030Scoping1
Bryn Rhudd Energy ParkBRYN RHUDD ENERGY PARK LIMITEDOnshore wind11431 Oct 2028High29 Dec 2030Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near Pont Abraham?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.