South Wales West Connection Node A 400kV: grid connection queue
South Wales West Connection Node A 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
6 projects with 1,825 MW are waiting to connect here (largest by capacity: battery storage, solar + storage). Contracted dates run from 30 Oct 2037 to 31 Oct 2037.
6projects in the queue
1,825 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Nant Helen | SOLAR SECURITIES LIMITED | Solar + storage | 500 | 30 Oct 2037 | Low | 30 Oct 2037 | Scoping | 1 |
| Swansea North-Rhigos Solar& BESS & Wind | TYLER HILL CONSULTING LIMITED | Mixed and other | 400 | 30 Oct 2037 | Low | 30 Oct 2037 | Scoping | 1 |
| Rhigos BESS | KONA ASSET 4 LIMITED | Battery storage | 225 | 30 Oct 2037 | Low | 30 Oct 2037 | Scoping | 1 |
| Rhigos BESS | REWE 11 Limited | Battery storage | 200 | 30 Oct 2037 | Low | 30 Oct 2037 | Scoping | 1 |
| Lightsource Rhigos BESS | Lightsource Renewable UK Development Limited | Battery storage | 300 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
| TH Maes Melin | FRV Powertek Limited | Battery storage | 200 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near South Wales West Connection Node A 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Pont Abraham: 1,241 MW waiting
- Pont Abraham 132KV: 253 MW waiting
- SOUTH WALES WEST CONNECTION NODE A 132KV: 150 MW waiting
- South Wales West Connection Node B 400kV: 700 MW waiting
- Swansea North 400kV: 2,021 MW waiting