Pont Abraham 132KV: grid connection queue
Pont Abraham 132KV · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 253 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Oct 2026 to 31 Oct 2026.
1project in the queue
253 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Nant Mithil Energy Park | NANT MITHIL ENERGY PARK LIMITED | Onshore wind | 253 | 31 Oct 2026 | n/a | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Pont Abraham 132KV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Pont Abraham: 1,241 MW waiting
- SOUTH WALES WEST CONNECTION NODE A 132KV: 150 MW waiting
- South Wales West Connection Node A 400kV: 1,825 MW waiting
- South Wales West Connection Node C 400kV: 288 MW waiting
- South Wales West Connection Node B 400kV: 700 MW waiting