Cilfynydd 400kV: grid connection queue
Cilfynydd 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
8 projects with 2,998 MW are waiting to connect here (largest by capacity: mixed and other, battery storage). Contracted dates run from 1 Apr 2027 to 15 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Twyn Hywel Cillfynydd | Twyn Hywel Energy Park Ltd | Onshore wind | 108 | 1 Apr 2027 | High | 29 May 2029 | Scoping | none |
| Merthyr Solar and Battery | EEW RENEWABLES LTD | Solar | 175 | 12 May 2029 | Medium | 12 May 2029 | Scoping | 1 |
| Cilfynydd Green Energy Centre | CILFYNYDD NG LIMITED | Mixed and other | 1,025 | 30 Oct 2029 | Medium | 30 Oct 2029 | Awaiting Consents | 1 |
| Cilfynydd | ENSO GREEN HOLDINGS X LIMITED | Mixed and other | 400 | 31 Oct 2030 | Medium | 31 Oct 2030 | Awaiting Consents | 1 |
| Penrhiwdarren Farm | QAIR RENEWABLES UK LIMITED | Battery storage | 500 | 15 Sep 2037 | Low | 15 Sep 2037 | Scoping | 1 |
| BESS Cilfynydd | REWE 2 LIMITED | Battery storage | 200 | 15 Sep 2037 | Low | 15 Sep 2037 | Scoping | 1 |
| Cilfynydd BESS | Cilfynydd BESS Limited | Battery storage | 350 | 15 Oct 2037 | Low | 15 Oct 2037 | Scoping | 1 |
| Cilfynydd 2 | REWE 8 LIMITED | Battery storage | 240 | 15 Oct 2037 | Low | 15 Oct 2037 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 4 times: 3 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 3 Nov 2026 | Cilfynydd BESS | 15 Sep 2037 | 15 Oct 2037 | +1 months |
| 13 Oct 2026 | Cilfynydd BESS | 15 Oct 2037 | 15 Sep 2037 | -1 months |
| 6 Oct 2026 | Cilfynydd Green Energy Centre | 30 Oct 2028 | 30 Oct 2029 | +12 months |
| 11 Aug 2026 | Cilfynydd Grid Stability Services | 31 Jul 2025 | 31 Mar 2027 | +20 months |
Thinking of connecting near Cilfynydd 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- South Wales East Node A 275kV: 699 MW waiting
- South Wales East Connection Node A 275kV: 95 MW waiting
- South Wales East Connection Node B 400kV: 249 MW waiting
- Hirwaun: 120 MW waiting
- Aberthaw 275kV: 1,004 MW waiting