Aberthaw 275kV: grid connection queue

Aberthaw 275kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

5 projects with 1,004 MW are waiting to connect here (largest by capacity: battery storage, solar + storage). Contracted dates run from 30 Oct 2028 to 30 Oct 2037.

5projects in the queue
1,004 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
1date moves since 2 Jun 2026
249 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Aberthaw EnergyABERTHAW ENERGY LIMITEDBattery storage24930 Oct 2028High30 Oct 2030Scoping1
Afon DdawLIGHTSOURCE SPV 214 LIMITEDSolar + storage24931 Oct 2029Medium31 Oct 2029Scopingnone
Aberthaw PV & BESS GenerationREWE 12 LimitedBattery storage20031 Oct 2029Medium31 Oct 2029Scoping1
Aberthaw (Tertiary)Aberthaw Green LimitedSolar + storage5731 Oct 2029Medium31 Oct 2029Scoping1
Mwyndy StorageCENIN RENEWABLES LIMITEDBattery storage24930 Oct 2037Low30 Oct 2037Scoping1

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
13 Oct 2026Aberthaw PV & BESS Generation30 Jun 202931 Oct 2029+4 months

Thinking of connecting near Aberthaw 275kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.