South Wales East Connection Node B 400kV: grid connection queue
South Wales East Connection Node B 400kV · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 249 MW is waiting to connect here (largest by capacity: mixed and other). Contracted dates run from 31 Oct 2037 to 31 Oct 2037.
1project in the queue
249 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Wern Tarw Storage | CENIN RENEWABLES LIMITED | Mixed and other | 249 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near South Wales East Connection Node B 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- South Wales East Connection Node A 275kV: 95 MW waiting
- Aberthaw 275kV: 1,004 MW waiting
- Aberthaw B 275/132kV: 240 MW waiting
- Imperial Park B 400kV: 1,400 MW waiting
- Imperial Park 400kV: 225 MW waiting