Imperial Park B 400kV: grid connection queue
Imperial Park B 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 1,400 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 6 Dec 2036 to 31 Oct 2037.
2projects in the queue
1,400 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| IPC Grid Tremorfa | IPC GRID CONNECTION LIMITED | Battery storage | 1,000 | 6 Dec 2036 | Low | 6 Dec 2036 | Scoping | 1 |
| TH Bridge Farm | FRV Powertek Limited | Battery storage | 400 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Imperial Park B 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Imperial Park 400kV: 225 MW waiting
- South Wales East Connection Node A 275kV: 95 MW waiting
- Whitson 275kV: 485 MW waiting
- South Wales East Connection Node B 400kV: 249 MW waiting
- Uskmouth 275kV: 249 MW waiting