Whitson 275kV: grid connection queue
Whitson 275kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
4 projects with 485 MW are waiting to connect here (largest by capacity: battery storage, solar). Contracted dates run from 31 Oct 2027 to 30 Oct 2037.
4projects in the queue
485 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
335 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Whitson | PIVOTED POWER LLP | Battery storage | 50 | 31 Oct 2027 | High | 30 Oct 2029 | Scoping | 1 |
| Llanwern Phase 2 | FUTURE ENERGY LLANWERN LIMITED | Solar | 190 | 1 Oct 2028 | High | 16 Oct 2030 | Awaiting Consents | none |
| Llanwern Phase 1 | FUTURE ENERGY LLANWERN LIMITED | Solar + storage | 95 | 1 Oct 2028 | High | 1 Oct 2030 | Awaiting Consents | none |
| Whitson BESS | FIELD DEVCO LTD | Battery storage | 150 | 30 Oct 2037 | Low | 30 Oct 2037 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Whitson 275kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Uskmouth 275kV: 249 MW waiting
- Uskmouth 132kV: 120 MW waiting
- Imperial Park B 400kV: 1,400 MW waiting
- Imperial Park 400kV: 225 MW waiting
- South Wales East Connection Node A 275kV: 95 MW waiting