Uskmouth 132kV: grid connection queue

Uskmouth 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 120 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2026 to 31 Oct 2026.

1project in the queue
120 MWwaiting to connect
360 MWalready connected
120 MWholding Gate 2
2date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Uskmouth - New ConnectionAW1 ENERGY STORAGE LIMITEDBattery storage12031 Oct 2026n/aUnder Construction/Commissioning2

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 1 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
20 Oct 2026Uskmouth - New Connection31 Oct 202731 Oct 2026-12 months
13 Oct 2026Uskmouth - New Connection31 Oct 202631 Oct 2027+12 months

Thinking of connecting near Uskmouth 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points