Uskmouth 132kV: grid connection queue
Uskmouth 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 120 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2026 to 31 Oct 2026.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Uskmouth - New Connection | AW1 ENERGY STORAGE LIMITED | Battery storage | 120 | 31 Oct 2026 | n/a | Under Construction/Commissioning | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 1 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 20 Oct 2026 | Uskmouth - New Connection | 31 Oct 2027 | 31 Oct 2026 | -12 months |
| 13 Oct 2026 | Uskmouth - New Connection | 31 Oct 2026 | 31 Oct 2027 | +12 months |
Thinking of connecting near Uskmouth 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Uskmouth 275kV: 249 MW waiting
- Whitson 275kV: 485 MW waiting
- Imperial Park B 400kV: 1,400 MW waiting
- Imperial Park 400kV: 225 MW waiting
- South Wales East Connection Node A 275kV: 95 MW waiting