Uskmouth 275kV: grid connection queue
Uskmouth 275kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 249 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 14 Jun 2029 to 14 Jun 2029.
1project in the queue
249 MWwaiting to connect
850 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| EcoUskmouth | AW2 ENERGY STORAGE LIMITED | Battery storage | 249 | 14 Jun 2029 | Medium | 14 Jun 2029 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Uskmouth 275kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Uskmouth 132kV: 120 MW waiting
- Whitson 275kV: 485 MW waiting
- Imperial Park B 400kV: 1,400 MW waiting
- Imperial Park 400kV: 225 MW waiting
- South Wales East Connection Node A 275kV: 95 MW waiting