Uskmouth 275kV: grid connection queue

Uskmouth 275kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 249 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 14 Jun 2029 to 14 Jun 2029.

1project in the queue
249 MWwaiting to connect
850 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
EcoUskmouthAW2 ENERGY STORAGE LIMITEDBattery storage24914 Jun 2029Medium14 Jun 2029Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near Uskmouth 275kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points