Drakelow 400kV: grid connection queue

Drakelow 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

7 projects with 2,994 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 1 Oct 2020 to 30 Oct 2037.

7projects in the queue
2,994 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
1,274 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Powersite @ DrakelowPOWERSITE LTDGas and thermal3801 Oct 2020n/aUnder Construction/Commissioningnone
Drakelow Green Energy CentreDRAKELOW NG LIMITEDSolar + storage1,02530 Apr 2028High30 Apr 2030Awaiting Consentsnone
Caldwell RoadTAGENERGY DEVELOPMENT UK LIMITEDBattery storage24930 Oct 2028High30 Oct 2030Scoping1
Greta IIITAGENERGY DEVELOPMENT UK LIMITEDSolar + storage50030 Oct 2029Medium30 Oct 2029Scoping1
Walton Road Energy ProjectLightsource Renewable UK Development LimitedSolar + storage24031 Oct 2029Medium31 Oct 2029Scoping1
Drakelow BESSHARMONY DL LTDBattery storage20031 Dec 2029Medium31 Dec 2029Consents Approvednone
Drakelow PV & BESS StationIBV Elford Park Solar LimitedSolar + storage40030 Oct 2037Low30 Oct 2037Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near Drakelow 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points