Willington East 400kV: grid connection queue
Willington East 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
4 projects with 402 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 30 Jun 2026 to 31 Oct 2033.
4projects in the queue
402 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
95 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Willington | PIVOTED POWER LLP | Battery storage | 57 | 30 Jun 2026 | n/a | Scoping | 1 | |
| Willington East 1 (Tertiary) | ENSO GREEN HOLDINGS U LIMITED | Solar + storage | 48 | 30 Oct 2027 | High | 29 Oct 2029 | Scoping | 1 |
| Willington East 2 (Tertiary) | ENSO GREEN HOLDINGS SS LIMITED | Solar + storage | 48 | 30 Jul 2028 | High | 30 Jul 2030 | Scoping | 1 |
| Willington PV & BESS | WILLINGTON ENERGY PARK LIMITED | Solar + storage | 250 | 31 Oct 2033 | Low | 31 Oct 2033 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Willington East 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Drakelow 400kV: 2,994 MW waiting
- Drakelow 132kV: 282 MW waiting
- Drakelow: 90 MW waiting
- Derbyshire Connection Node I 400kV: 968 MW waiting
- Derbyshire Connection Node C 400kV: 1,000 MW waiting