Drakelow 132kV: grid connection queue

Drakelow 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

2 projects with 282 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 30 Jun 2027 to 1 Dec 2027.

2projects in the queue
282 MWwaiting to connect
0 MWalready connected
162 MWholding Gate 2
1date moves since 2 Jun 2026
282 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Oaklands Farm Solar PVOAKLANDS FARM SOLAR LIMITED.Solar + storage16230 Jun 2027High29 Jun 2029Consents Approved2
DrakelowENSO GREEN HOLDINGS V LIMITEDBattery storage1201 Dec 2027High30 Nov 2029Scoping1

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
18 Aug 2026Royle Farm BESS31 Oct 202731 Oct 2028+12 months

Thinking of connecting near Drakelow 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points