Drakelow 132kV: grid connection queue
Drakelow 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 282 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 30 Jun 2027 to 1 Dec 2027.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Oaklands Farm Solar PV | OAKLANDS FARM SOLAR LIMITED. | Solar + storage | 162 | 30 Jun 2027 | High | 29 Jun 2029 | Consents Approved | 2 |
| Drakelow | ENSO GREEN HOLDINGS V LIMITED | Battery storage | 120 | 1 Dec 2027 | High | 30 Nov 2029 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 18 Aug 2026 | Royle Farm BESS | 31 Oct 2027 | 31 Oct 2028 | +12 months |
Thinking of connecting near Drakelow 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Drakelow 400kV: 2,994 MW waiting
- Drakelow: 90 MW waiting
- Willington East 400kV: 402 MW waiting
- Harlaston 400kV: 600 MW waiting
- Rugeley 400kV: 600 MW waiting