Derbyshire Connection Node I 400kV: grid connection queue

Derbyshire Connection Node I 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

3 projects with 968 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 30 Oct 2037 to 30 Oct 2037.

3projects in the queue
968 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Long Buckby Solar/BESSGreentech Invest UK (17) LimitedSolar + storage50030 Oct 2037Low30 Oct 2037Scoping1
Lightsource Patford BridgeLightsource Renewable UK Development LimitedSolar + storage24030 Oct 2037Low30 Oct 2037Scoping1
Patford Bridge BESSKona Energy LimitedBattery storage22830 Oct 2037Low30 Oct 2037Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near Derbyshire Connection Node I 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.