Derbyshire Connection Node I 400kV: grid connection queue
Derbyshire Connection Node I 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
3 projects with 968 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 30 Oct 2037 to 30 Oct 2037.
3projects in the queue
968 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Long Buckby Solar/BESS | Greentech Invest UK (17) Limited | Solar + storage | 500 | 30 Oct 2037 | Low | 30 Oct 2037 | Scoping | 1 |
| Lightsource Patford Bridge | Lightsource Renewable UK Development Limited | Solar + storage | 240 | 30 Oct 2037 | Low | 30 Oct 2037 | Scoping | 1 |
| Patford Bridge BESS | Kona Energy Limited | Battery storage | 228 | 30 Oct 2037 | Low | 30 Oct 2037 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Derbyshire Connection Node I 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Willington 400kV: 2,125 MW waiting
- DERBYSHIRE CONNECTION NODE E 132KV SUBSTATION: 240 MW waiting
- Derbyshire Connection Node C 400kV: 1,000 MW waiting
- ERBYSHIRE CONNECTION NODE E 132kV SUBSTATION: 240 MW waiting
- Derbyshire Connection Node F 132KV: 350 MW waiting