Willington 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

3 projects with 2,125 MW are waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 30 Oct 2028 to 30 Oct 2029.

3projects in the queue
2,125 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
1date moves since 2 Jun 2026
1,525 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Willington Green Energy CentreWILLINGTON NG LIMITEDSolar + storage1,02530 Oct 2028High30 Oct 2030Awaiting Consentsnone
Willington Energy ParkBROCKWELL STORAGE & SOLAR LIMITEDSolar + storage50031 Oct 2028High31 Oct 2030Scopingnone
WillingtonSSE UTILITY SOLUTIONS LIMITEDSolar + storage60030 Oct 2029Medium30 Oct 2029Scoping1

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
29 Sep 2026Willington Energy Park30 Mar 202831 Oct 2028+7 months

Thinking of connecting near Willington 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points