Thurcroft 275kV: grid connection queue
Thurcroft 275kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 500 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 31 Oct 2031 to 31 Oct 2034.
2projects in the queue
500 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Thurcroft BESS | HARMONY TC LIMITED | Battery storage | 100 | 31 Oct 2031 | Medium | 31 Oct 2031 | Scoping | 1 |
| MALTBY DEV. | Firma Vogt Solar Ltd | Solar + storage | 400 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Thurcroft 275kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Brinsworth 400kV: 1,500 MW waiting
- Brinsworth B 400kV: 600 MW waiting
- Thorpe Marsh 400kV: 2,720 MW waiting
- Thorpe Marsh: 180 MW waiting
- Pitsmoor: 90 MW waiting