Thorpe Marsh 400kV: grid connection queue

Thorpe Marsh 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

4 projects with 2,720 MW are waiting to connect here (largest by capacity: battery storage, mixed and other). Contracted dates run from 30 Jan 2027 to 16 Apr 2032.

4projects in the queue
2,720 MWwaiting to connect
0 MWalready connected
1,400 MWholding Gate 2
0date moves since 2 Jun 2026
1,457 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Thorpe Marsh Energy ParkTHORPE MARSH GREEN ENERGY HUB LIMITEDBattery storage1,40030 Jan 2027High29 Jan 2029Under Construction/Commissioning2
Thorpe Marsh 1 (Tertiary)ENSO GREEN HOLDINGS I LIMITEDSolar + storage5730 Oct 2028High30 Oct 2030Consents Approvednone
Thorpe Marsh Green Energy CentreTHORPE MARSH NG LTDMixed and other1,02530 Oct 2030Medium30 Oct 2030Awaiting Consentsnone
Fenwick Solar ProjectFENWICK SOLAR PROJECT LIMITEDSolar + storage23816 Apr 2032Low16 Apr 2032Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near Thorpe Marsh 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.