Thorpe Marsh 400kV: grid connection queue
Thorpe Marsh 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
4 projects with 2,720 MW are waiting to connect here (largest by capacity: battery storage, mixed and other). Contracted dates run from 30 Jan 2027 to 16 Apr 2032.
4projects in the queue
2,720 MWwaiting to connect
0 MWalready connected
1,400 MWholding Gate 2
0date moves since 2 Jun 2026
1,457 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Thorpe Marsh Energy Park | THORPE MARSH GREEN ENERGY HUB LIMITED | Battery storage | 1,400 | 30 Jan 2027 | High | 29 Jan 2029 | Under Construction/Commissioning | 2 |
| Thorpe Marsh 1 (Tertiary) | ENSO GREEN HOLDINGS I LIMITED | Solar + storage | 57 | 30 Oct 2028 | High | 30 Oct 2030 | Consents Approved | none |
| Thorpe Marsh Green Energy Centre | THORPE MARSH NG LTD | Mixed and other | 1,025 | 30 Oct 2030 | Medium | 30 Oct 2030 | Awaiting Consents | none |
| Fenwick Solar Project | FENWICK SOLAR PROJECT LIMITED | Solar + storage | 238 | 16 Apr 2032 | Low | 16 Apr 2032 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Thorpe Marsh 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Thorpe Marsh: 180 MW waiting
- Trent Valley North Connection Node B 400kV: 1,450 MW waiting
- Tween Bridge 400kV: 1,000 MW waiting
- Thurcroft 275kV: 500 MW waiting
- Eggborough 400kV: 3,000 MW waiting