Trent Valley North Connection Node B 400kV: grid connection queue
Trent Valley North Connection Node B 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
3 projects with 1,450 MW are waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 30 Oct 2029 to 30 Oct 2035.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Tween Bridge Solar Park | RWE Renewables UK Solar and Storage Limited | Solar + storage | 800 | 30 Oct 2029 | Medium | 30 Oct 2029 | Scoping | none |
| Kinoulton Solar & BESS | GREENTECH INVEST UK (16) LIMITED | Solar + storage | 500 | 30 Oct 2034 | Low | 30 Oct 2034 | Scoping | 1 |
| Epworth PV & BESS Station | IBV KELFIELD SOLAR LTD | Solar + storage | 150 | 30 Oct 2035 | Low | 30 Oct 2035 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 0 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 13 Oct 2026 | Epworth PV & BESS Station | 31 Oct 2037 | 30 Oct 2035 | -24 months |
Thinking of connecting near Trent Valley North Connection Node B 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Tween Bridge 400kV: 1,000 MW waiting
- Drax 400kV: 4,306 MW waiting
- Drax 132kV: 190 MW waiting
- Thorpe Marsh 400kV: 2,720 MW waiting
- Thorpe Marsh: 180 MW waiting