Drax 400kV: grid connection queue
Drax 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 4,306 MW are waiting to connect here (largest by capacity: mixed and other, solar). Contracted dates run from 30 Sep 2029 to 30 Oct 2035.
2projects in the queue
4,306 MWwaiting to connect
3,906 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Drax Solar | East Yorkshire Solar Farm Limited | Solar | 400 | 30 Sep 2029 | Medium | 30 Sep 2029 | Scoping | none |
| Drax BECCS | Drax Power Limited | Mixed and other | 3,906 | 30 Oct 2035 | Low | 30 Oct 2035 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Drax 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Drax 132kV: 190 MW waiting
- Eggborough 400kV: 3,000 MW waiting
- Leeds North Connection Node B 400kV: 1,442 MW waiting
- Trent Valley North Connection Node B 400kV: 1,450 MW waiting
- Tween Bridge 400kV: 1,000 MW waiting