Drax 400kV: grid connection queue

Drax 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

2 projects with 4,306 MW are waiting to connect here (largest by capacity: mixed and other, solar). Contracted dates run from 30 Sep 2029 to 30 Oct 2035.

2projects in the queue
4,306 MWwaiting to connect
3,906 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Drax SolarEast Yorkshire Solar Farm LimitedSolar40030 Sep 2029Medium30 Sep 2029Scopingnone
Drax BECCSDrax Power LimitedMixed and other3,90630 Oct 2035Low30 Oct 2035Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near Drax 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points