Benzene

Leeds North Connection Node B 400kV: grid connection queue

Leeds North Connection Node B 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

5 projects with 1,442 MW are waiting to connect here (largest by capacity: battery storage, mixed and other). Contracted dates run from 30 Oct 2035 to 31 Oct 2035.

5projects in the queue
1,442 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
1date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Pollington HybridEDF ENERGY RENEWABLES LIMITEDMixed and other44030 Oct 2035Low30 Oct 2035Scoping1
Calderdale Wind Farm 312MWCALDERDALE WIND FARM LTDOnshore wind31230 Oct 2035Low30 Oct 2035Scopingnone
Lightsource New EggboroughLightsource Renewable UK Development LimitedOnshore wind + storage24030 Oct 2035Low30 Oct 2035Scoping1
Eggborough BESSFig Power LimitedBattery storage20030 Oct 2035Low30 Oct 2035Scoping1
Jackdaw BESSDowning Renewable Developments LLPBattery storage25031 Oct 2035Low31 Oct 2035Scoping1

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 0 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
3 Nov 2026Jackdaw BESS31 Oct 203631 Oct 2035-12 months

Thinking of connecting near Leeds North Connection Node B 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points