Monk Fryston 400kV: grid connection queue

Monk Fryston 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

3 projects with 1,700 MW are waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 31 Dec 2029 to 24 Oct 2035.

3projects in the queue
1,700 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Monk FrystonLight Valley Solar LimitedSolar + storage50031 Dec 2029Medium31 Dec 2029Scopingnone
Monk FrystonENSO GREEN HOLDINGS X LIMITEDSolar + storage40031 Oct 2031Medium31 Oct 2031Scoping1
Monk Fryston Energy ParkELEMENTS GREEN DEVELOPMENT LTDSolar + storage80024 Oct 2035Low24 Oct 2035Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near Monk Fryston 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.