Ferrybridge C 275kV: grid connection queue

Ferrybridge C 275kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

2 projects with 1,670 MW are waiting to connect here (largest by capacity: mixed and other, solar + storage). Contracted dates run from 4 Oct 2030 to 24 Oct 2035.

2projects in the queue
1,670 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Ferrybridge DKeadby Generation LimitedMixed and other1,4204 Oct 2030Medium4 Oct 2030Awaiting Consentsnone
Ferrybridge C PV & BESS SubstationO&G Solar (SPV 19) LimitedSolar + storage25024 Oct 2035Low24 Oct 2035Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near Ferrybridge C 275kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.