Ferrybridge C 275kV: grid connection queue
Ferrybridge C 275kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 1,670 MW are waiting to connect here (largest by capacity: mixed and other, solar + storage). Contracted dates run from 4 Oct 2030 to 24 Oct 2035.
2projects in the queue
1,670 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Ferrybridge D | Keadby Generation Limited | Mixed and other | 1,420 | 4 Oct 2030 | Medium | 4 Oct 2030 | Awaiting Consents | none |
| Ferrybridge C PV & BESS Substation | O&G Solar (SPV 19) Limited | Solar + storage | 250 | 24 Oct 2035 | Low | 24 Oct 2035 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Ferrybridge C 275kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Kellingley IDNO: 440 MW waiting
- Kellingley 400kV: 250 MW waiting
- Monk Fryston 400kV: 1,700 MW waiting
- Monk Fryston 275kV: 970 MW waiting
- Leeds North Connection Node B 400kV: 1,442 MW waiting