Monk Fryston 275kV: grid connection queue

Monk Fryston 275kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

4 projects with 970 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2025 to 2 Jun 2036.

4projects in the queue
970 MWwaiting to connect
57 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Monk Fryston SSESSE BATTERY MONK FRYSTON LIMITEDBattery storage32031 Oct 2025n/aConsents Approvednone
Monk Fryston BESSHARMONY MF LIMITEDBattery storage20031 Oct 2029Medium31 Oct 2029Scopingnone
Monk FrystonDowning Renewable Developments LLPBattery storage25030 Oct 2035Low30 Oct 2035Scoping1
Kingfisher FarmREWE 6 LIMITEDBattery storage2002 Jun 2036Low2 Jun 2036Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near Monk Fryston 275kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points