Monk Fryston 275kV: grid connection queue
Monk Fryston 275kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
4 projects with 970 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2025 to 2 Jun 2036.
4projects in the queue
970 MWwaiting to connect
57 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Monk Fryston SSE | SSE BATTERY MONK FRYSTON LIMITED | Battery storage | 320 | 31 Oct 2025 | n/a | Consents Approved | none | |
| Monk Fryston BESS | HARMONY MF LIMITED | Battery storage | 200 | 31 Oct 2029 | Medium | 31 Oct 2029 | Scoping | none |
| Monk Fryston | Downing Renewable Developments LLP | Battery storage | 250 | 30 Oct 2035 | Low | 30 Oct 2035 | Scoping | 1 |
| Kingfisher Farm | REWE 6 LIMITED | Battery storage | 200 | 2 Jun 2036 | Low | 2 Jun 2036 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Monk Fryston 275kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Monk Fryston 400kV: 1,700 MW waiting
- Leeds North Connection Node B 400kV: 1,442 MW waiting
- Kellingley IDNO: 440 MW waiting
- Kellingley 400kV: 250 MW waiting
- Ferrybridge C 275kV: 1,670 MW waiting