Eggborough 400kV: grid connection queue
Eggborough 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 3,000 MW are waiting to connect here (largest by capacity: mixed and other, battery storage). Contracted dates run from 1 Oct 2026 to 16 Jun 2032.
2projects in the queue
3,000 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Eggborough CCGT - OCGT - BESS | EGGBOROUGH POWER LIMITED | Mixed and other | 2,450 | 1 Oct 2026 | n/a | Awaiting Consents | none | |
| Eggborough | SSE EGGBOROUGH LIMITED | Battery storage | 550 | 16 Jun 2032 | Low | 16 Jun 2032 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Eggborough 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Leeds North Connection Node B 400kV: 1,442 MW waiting
- Kellingley IDNO: 440 MW waiting
- Kellingley 400kV: 250 MW waiting
- Monk Fryston 400kV: 1,700 MW waiting
- Monk Fryston 275kV: 970 MW waiting