Tween Bridge 400kV: grid connection queue
Tween Bridge 400kV · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 1,000 MW is waiting to connect here (largest by capacity: mixed and other). Contracted dates run from 30 Oct 2035 to 30 Oct 2035.
1project in the queue
1,000 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| ER BR Energy | ER PROJECT DEVELOPMENT CO LIMITED | Mixed and other | 1,000 | 30 Oct 2035 | Low | 30 Oct 2035 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Tween Bridge 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Trent Valley North Connection Node B 400kV: 1,450 MW waiting
- Drax 400kV: 4,306 MW waiting
- Drax 132kV: 190 MW waiting
- Thorpe Marsh 400kV: 2,720 MW waiting
- Thorpe Marsh: 180 MW waiting