Thorpe Marsh: grid connection queue

Thorpe Marsh GSP · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 180 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2035 to 31 Oct 2035.

1project in the queue
180 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
NEL NicholsonUE 2 LTDBattery storage18031 Oct 2035Low31 Oct 2035Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near Thorpe Marsh?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points