CARRADALE 3 132/33KV GRID SUPPLY POINT SUBSTATION: grid connection queue
CARRADALE 3 132/33KV GRID SUPPLY POINT SUBSTATION · SSEN Transmission (northern Scotland) · register of 26 November 2026
2 projects with 125 MW are waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Oct 2034 to 31 Oct 2035.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Killean Wind Farm | Renewable Energy Systems Limited | Onshore wind | 60 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
| Allt Domhain Wind Farm | ENERGYFARM ALLT DOMHAIN LTD | Onshore wind | 65 | 31 Oct 2035 | Low | 31 Oct 2035 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Dippen Primary | SSEN Distribution | 3.6 km | 0 MW | 0.7 MW |
| Carradale 1 GSP | SSEN Distribution | 4.7 km | ||
| Carradale 2 GSP | SSEN Distribution | 4.7 km | ||
| Balliekine Primary | SSEN Distribution | 7.4 km | 0 MW | 0 MW |
| Machrie Primary | SSEN Distribution | 8.7 km | 0 MW | 0 MW |
| Campbeltown Primary | SSEN Distribution | 16.7 km | 0 MW | 8.3 MW |
Thinking of connecting near CARRADALE 3 132/33KV GRID SUPPLY POINT SUBSTATION?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- NEW CARRADALE 132KV SUBSTATION: 160 MW waiting
- Carradale 1: 73 MW waiting
- Carradale 2 132/33kV GSP: 50 MW waiting
- Beinn an Tuirc: 95 MW waiting
- DEUCHERAN HILL 2 132KV SUBSTATION: 165 MW waiting