DEUCHERAN HILL 2 132KV SUBSTATION: grid connection queue
DEUCHERAN HILL 2 132KV SUBSTATION · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 165 MW is waiting to connect here (largest by capacity: onshore wind + storage). Contracted dates run from 31 Oct 2034 to 31 Oct 2034.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Deucheran Hill 2 Wind Farm | RWE Renewables UK Onshore Wind Limited | Onshore wind + storage | 165 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 1 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 20 Oct 2026 | Deucheran Hill 2 Wind Farm | 1 Apr 2031 | 31 Oct 2034 | +43 months |
| 13 Oct 2026 | Deucheran Hill 2 Wind Farm | 31 Oct 2034 | 1 Apr 2031 | -43 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Carradale 2 GSP | SSEN Distribution | 5.1 km | ||
| Carradale 1 GSP | SSEN Distribution | 5.1 km | ||
| Dippen Primary | SSEN Distribution | 6.2 km | 0 MW | 0.7 MW |
| Ballure Primary | SSEN Distribution | 8.9 km | 0 MW | 1.6 MW |
| Balliekine Primary | SSEN Distribution | 11.0 km | 0 MW | 0 MW |
| Machrie Primary | SSEN Distribution | 16.0 km | 0 MW | 0 MW |
Thinking of connecting near DEUCHERAN HILL 2 132KV SUBSTATION?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Beinn an Tuirc: 95 MW waiting
- High Constellation 132/33kV: 50 MW waiting
- NEW CARRADALE 132KV SUBSTATION: 160 MW waiting
- CARRADALE 3 132/33KV GRID SUPPLY POINT SUBSTATION: 125 MW waiting
- Carradale 1: 73 MW waiting