High Constellation 132/33kV: grid connection queue
High Constellation 132/33kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 50 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Oct 2028 to 31 Oct 2028.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| High Constellation Windfarm | HIGH CONSTELLATION WINDFARM LIMITED | Onshore wind | 50 | 31 Oct 2028 | High | 29 Dec 2030 | Consents Approved | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 4 Aug 2026 | High Constellation Windfarm | 31 Jul 2027 | 31 Oct 2028 | +15 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Claonaig Primary | SSEN Distribution | 8.1 km | 0 MW | 0.3 MW |
| Ballure Primary | SSEN Distribution | 9.6 km | 0 MW | 1.6 MW |
| Carradale 2 GSP | SSEN Distribution | 12.6 km | ||
| Carradale 1 GSP | SSEN Distribution | 12.6 km | ||
| Dippen Primary | SSEN Distribution | 13.4 km | 0 MW | 0.7 MW |
| Balliekine Primary | SSEN Distribution | 13.7 km | 0 MW | 0 MW |
Thinking of connecting near High Constellation 132/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Sheirdrim 132kV: 84 MW waiting
- DEUCHERAN HILL 2 132KV SUBSTATION: 165 MW waiting
- Earraghail 275/33KV: 105 MW waiting
- Beinn an Tuirc: 95 MW waiting
- NEW CARRADALE 132KV SUBSTATION: 160 MW waiting