Benzene

Beinn an Tuirc: grid connection queue

Beinn an Tuirc Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 95 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Oct 2034 to 31 Oct 2034.

1project in the queue
95 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Beinn an Tuirc 1ScottishPower Renewables (UK) LimitedOnshore wind9531 Oct 2034Low31 Oct 2034Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Carradale 1 GSPSSEN Distribution5.7 km
Carradale 2 GSPSSEN Distribution5.7 km
Dippen PrimarySSEN Distribution6.1 km0 MW0.7 MW
Ballure PrimarySSEN Distribution13.3 km0 MW1.6 MW
Balliekine PrimarySSEN Distribution13.4 km0 MW0 MW
Campbeltown PrimarySSEN Distribution16.3 km0 MW8.3 MW

Thinking of connecting near Beinn an Tuirc?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points