Carradale 1: grid connection queue

Carradale 1 GSP · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 73 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 30 Apr 2030 to 30 Apr 2030.

1project in the queue
73 MWwaiting to connect
129 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
73 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Narachan Wind FarmENERGYFARM UK NARACHAN LLPOnshore wind7330 Apr 2030High16 Mar 2032Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Dippen PrimarySSEN Distribution3.6 km0 MW0.7 MW
Carradale 1 GSPSSEN Distribution4.7 km
Carradale 2 GSPSSEN Distribution4.7 km
Balliekine PrimarySSEN Distribution7.4 km0 MW0 MW
Machrie PrimarySSEN Distribution8.7 km0 MW0 MW
Campbeltown PrimarySSEN Distribution16.7 km0 MW8.3 MW

Thinking of connecting near Carradale 1?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points