Balliemeanoch 275kV: grid connection queue

Balliemeanoch 275kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 900 MW is waiting to connect here (largest by capacity: hydro, pumped storage and tidal). Contracted dates run from 31 Oct 2034 to 31 Oct 2034.

1project in the queue
900 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Balliemeanoch PSHILI (Borders PSH) LtdHydro, pumped storage and tidal90031 Oct 2034Low31 Oct 2034Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Eredine PrimarySSEN Distribution6.8 km0 MW0.2 MW
Kilchrenan PrimarySSEN Distribution9.2 km0 MW0.4 MW
Inveraray PrimarySSEN Distribution9.7 km2.5 MW2 MW
Cromalt PrimarySSEN Distribution10.3 km0 MW0 MW
Strachur PrimarySSEN Distribution15.8 km0.6 MW0.3 MW
Taynuilt GSPSSEN Distribution16.1 km

Thinking of connecting near Balliemeanoch 275kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.