Cruachan 275kV: grid connection queue
Cruachan 275kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
2 projects with 640 MW are waiting to connect here (largest by capacity: hydro, pumped storage and tidal). Contracted dates run from 4 Apr 2029 to 31 Oct 2030.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Cruachan U3&4 Replacement | DRAX PUMPED STORAGE LIMITED | Hydro, pumped storage and tidal | 40 | 4 Apr 2029 | Medium | 4 Apr 2029 | Consents Approved | 2 |
| Cruachan Expansion | Drax Cruachan Expansion Limited | Hydro, pumped storage and tidal | 600 | 31 Oct 2030 | Medium | 31 Oct 2030 | Scoping | none |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 1 Sep 2026 | Cruachan U3&4 Replacement | 1 Jun 2027 | 4 Apr 2029 | +22 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Kilchrenan Primary | SSEN Distribution | 5.3 km | 0 MW | 0.4 MW |
| Taynuilt GSP | SSEN Distribution | 7.4 km | ||
| Taynuilt Primary | SSEN Distribution | 7.5 km | 0 MW | 1.5 MW |
| Dalmally Primary | SSEN Distribution | 7.6 km | 0 MW | 1.1 MW |
| Dalmally School Primary | SSEN Distribution | 9.3 km | 0 MW | 0.1 MW |
| Kenmore Primary | SSEN Distribution | 10.5 km | 0 MW | 1.6 MW |
Thinking of connecting near Cruachan 275kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Creag Dhubh 275/132/33kV: 68 MW waiting
- Balliemeanoch 275kV: 900 MW waiting
- Blarghour: 67 MW waiting
- Clachan 2 132/33kV GSP: 27 MW waiting
- Creag Dhubh Wind Farm and BESS 132kV: 171 MW waiting