Blarghour: grid connection queue
Blarghour Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 67 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 1 Apr 2029 to 1 Apr 2029.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Blarghour Wind | BLARGHOUR WIND FARM LIMITED | Onshore wind | 67 | 1 Apr 2029 | High | 16 Feb 2031 | Consents Approved | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Inveraray Primary | SSEN Distribution | 6.5 km | 2.5 MW | 2 MW |
| Cromalt Primary | SSEN Distribution | 7.3 km | 0 MW | 0 MW |
| Eredine Primary | SSEN Distribution | 7.7 km | 0 MW | 0.2 MW |
| Kilchrenan Primary | SSEN Distribution | 10.5 km | 0 MW | 0.4 MW |
| Strachur Primary | SSEN Distribution | 13.1 km | 0.6 MW | 0.3 MW |
| Ardkinglas GSP | SSEN Distribution | 13.5 km |
Thinking of connecting near Blarghour?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Balliemeanoch 275kV: 900 MW waiting
- Creag Dhubh 275/132/33kV: 68 MW waiting
- Creag Dhubh Wind Farm and BESS 132kV: 171 MW waiting
- Clachan 2 132/33kV GSP: 27 MW waiting
- Cruachan 275kV: 640 MW waiting