Clachan 2 132/33kV GSP: grid connection queue

Clachan 2 132/33kV GSP Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 27 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Oct 2032 to 31 Oct 2032.

1project in the queue
27 MWwaiting to connect
0 MWalready connected
27 MWholding Gate 2
1date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Creag DhubhMUIRDEN ENERGY LLPOnshore wind2731 Oct 2032Low31 Oct 2032Consents Approved2

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
17 Nov 2026Creag Dhubh31 Oct 203031 Oct 2032+24 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Butterbridge PrimarySSEN Distribution3.4 km0.1 MW0.1 MW
Clachan GSPSSEN Distribution6.0 km
Ardkinglas GSPSSEN Distribution6.6 km
Lochgoilhead PrimarySSEN Distribution7.0 km0 MW1.9 MW
Inveraray PrimarySSEN Distribution7.6 km2.5 MW2 MW
Cromalt PrimarySSEN Distribution8.2 km0 MW0 MW

Thinking of connecting near Clachan 2 132/33kV GSP?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.