Clachan 2 132/33kV GSP: grid connection queue
Clachan 2 132/33kV GSP Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 27 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Oct 2032 to 31 Oct 2032.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Creag Dhubh | MUIRDEN ENERGY LLP | Onshore wind | 27 | 31 Oct 2032 | Low | 31 Oct 2032 | Consents Approved | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 17 Nov 2026 | Creag Dhubh | 31 Oct 2030 | 31 Oct 2032 | +24 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Butterbridge Primary | SSEN Distribution | 3.4 km | 0.1 MW | 0.1 MW |
| Clachan GSP | SSEN Distribution | 6.0 km | ||
| Ardkinglas GSP | SSEN Distribution | 6.6 km | ||
| Lochgoilhead Primary | SSEN Distribution | 7.0 km | 0 MW | 1.9 MW |
| Inveraray Primary | SSEN Distribution | 7.6 km | 2.5 MW | 2 MW |
| Cromalt Primary | SSEN Distribution | 8.2 km | 0 MW | 0 MW |
Thinking of connecting near Clachan 2 132/33kV GSP?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Creag Dhubh Wind Farm and BESS 132kV: 171 MW waiting
- Creag Dhubh 275/132/33kV: 68 MW waiting
- Blarghour: 67 MW waiting
- Balliemeanoch 275kV: 900 MW waiting
- Cruachan 275kV: 640 MW waiting