Creag Dhubh 275/132/33kV: grid connection queue
Creag Dhubh 275/132/33kV · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 68 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2029 to 31 Oct 2029.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Ladyfield Renewable Energy Park | Ladyfield Renewable Energy Park Ltd | Battery storage | 68 | 31 Oct 2029 | Medium | 31 Oct 2029 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Inveraray Primary | SSEN Distribution | 4.4 km | 2.5 MW | 2 MW |
| Cromalt Primary | SSEN Distribution | 6.5 km | 0 MW | 0 MW |
| Ardkinglas GSP | SSEN Distribution | 7.8 km | ||
| Clachan GSP | SSEN Distribution | 9.9 km | ||
| Butterbridge Primary | SSEN Distribution | 10.8 km | 0.1 MW | 0.1 MW |
| Kilchrenan Primary | SSEN Distribution | 11.3 km | 0 MW | 0.4 MW |
Thinking of connecting near Creag Dhubh 275/132/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Blarghour: 67 MW waiting
- Balliemeanoch 275kV: 900 MW waiting
- Clachan 2 132/33kV GSP: 27 MW waiting
- Creag Dhubh Wind Farm and BESS 132kV: 171 MW waiting
- Cruachan 275kV: 640 MW waiting