Fife Energy Centre 132kV substation: grid connection queue

Fife Energy Centre 132kV substation · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 100 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2028 to 31 Oct 2028.

1project in the queue
100 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
100 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Fife Energy CentreCAMBRIDGE POWER LIMITEDBattery storage10031 Oct 2028High31 Oct 2030Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near Fife Energy Centre 132kV substation?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.