Biggleswade 400kV: grid connection queue
Biggleswade 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
7 projects with 3,056 MW are waiting to connect here (largest by capacity: solar + storage, mixed and other). Contracted dates run from 28 Sep 2029 to 31 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Biggleswade BESS | Central Bedfordshire Council | Battery storage | 57 | 28 Sep 2029 | Medium | 28 Sep 2029 | Scoping | 1 |
| Biggleswade PV | CSE38 LIMITED | Solar + storage | 50 | 31 Oct 2031 | Medium | 31 Oct 2031 | Awaiting Consents | 1 |
| Biggleswade | Biggleswade 10 Renewables Limited | Solar + storage | 1,000 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
| Biggleswade High Impact Green Energy Hub | TELIS ENERGY UK LIMITED | Mixed and other | 1,000 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
| Greengage Farm | Renewable Energy Systems Limited | Solar + storage | 500 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
| Biggleswade BESS | HARMONY BW LTD | Battery storage | 200 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | none |
| Noventum - Biggleswade | NOVENTUM POWER SOLAR 7 LIMITED | Solar + storage | 249 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 0 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 13 Oct 2026 | Biggleswade BESS | 31 Oct 2029 | 28 Sep 2029 | -1 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Biggleswade Primary 11kV | UK Power Networks | 0.5 km | 17 MW | 2.3 MW |
| Sandy Primary 11kV | UK Power Networks | 4.8 km | 27 MW | 8.7 MW |
| Shefford Primary 11kV | UK Power Networks | 7.1 km | 21 MW | 10 MW |
| West Letchworth Primary 11kV | UK Power Networks | 10.9 km | 12 MW | 7.1 MW |
| Letchworth Grid 33kV | UK Power Networks | 10.9 km | 94 MW | 19 MW |
| Letchworth Factory 11kV | UK Power Networks | 11.9 km | 33 MW | 9.9 MW |
Thinking of connecting near Biggleswade 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- West Anglia Connection Node I 400kV substation: 2,340 MW waiting
- West Anglia Connection Node D 400kV: 1,570 MW waiting
- Wymondley 400kV: 1,492 MW waiting
- Wymondley 2 400kV: 949 MW waiting
- Wymondley 400/33kV: 50 MW waiting