Wymondley 400/33kV: grid connection queue
Wymondley 400/33kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 50 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 30 May 2027 to 30 May 2027.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Wymondley Solar Farm | AGR SOLAR 4 LIMITED | Solar + storage | 50 | 30 May 2027 | High | 29 May 2029 | Consents Approved | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 22 Sep 2026 | Wymondley Solar Farm | 31 Oct 2025 | 30 May 2027 | +19 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| East Letchworth Primary 11kV | UK Power Networks | 4.1 km | 16 MW | 2.2 MW |
| Letchworth Factory 11kV | UK Power Networks | 4.6 km | 33 MW | 9.9 MW |
| Verity Way Primary 11kV | UK Power Networks | 6.4 km | 22 MW | 6.3 MW |
| West Letchworth Primary 11kV | UK Power Networks | 7.4 km | 12 MW | 7.1 MW |
| Letchworth Grid 33kV | UK Power Networks | 7.4 km | 94 MW | 19 MW |
| North Stevenage Primary 11kV | UK Power Networks | 7.9 km | 23 MW | 9.7 MW |
Thinking of connecting near Wymondley 400/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Wymondley 400kV: 1,492 MW waiting
- Wymondley 2 400kV: 949 MW waiting
- Cottered 400kV: 850 MW waiting
- Biggleswade 400kV: 3,056 MW waiting
- West Anglia Connection Node I 400kV substation: 2,340 MW waiting