Cottered 400kV: grid connection queue
Cottered 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 850 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 1 Jul 2032 to 1 Jul 2032.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Buntington GEC | BUNTINGTON GREEN ENERGY CENTRE LTD | Solar + storage | 850 | 1 Jul 2032 | Low | 1 Jul 2032 | Awaiting Consents | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Cherry Grn Primary 11kV | UK Power Networks | 4.2 km | 6.5 MW | -1.6 MW |
| Reed Primary 11kV | UK Power Networks | 7.0 km | 1.5 MW | -2.3 MW |
| Verity Way Primary 11kV | UK Power Networks | 7.8 km | 22 MW | 6.3 MW |
| Stevenage Grid 33kV | UK Power Networks | 9.1 km | 105 MW | 27 MW |
| East Letchworth Primary 11kV | UK Power Networks | 9.5 km | 16 MW | 2.2 MW |
| North Stevenage Primary 11kV | UK Power Networks | 9.9 km | 23 MW | 9.7 MW |
Thinking of connecting near Cottered 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Wymondley 400kV: 1,492 MW waiting
- Wymondley 2 400kV: 949 MW waiting
- Wymondley 400/33kV: 50 MW waiting
- Biggleswade 400kV: 3,056 MW waiting
- Jersey Farm 400kV: 400 MW waiting