Wymondley 2 400kV: grid connection queue

Wymondley 2 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

2 projects with 949 MW are waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 30 Oct 2032 to 31 Oct 2033.

2projects in the queue
949 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Wymondley GEC (Ethos Green)WYMONDLEY GREEN ENERGY CENTRE LTDSolar + storage70030 Oct 2032Low30 Oct 2032Awaiting Consents1
EcoWymondleyEconergy International LimitedSolar + storage24931 Oct 2033Low31 Oct 2033Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
East Letchworth Primary 11kVUK Power Networks4.1 km16 MW2.2 MW
Letchworth Factory 11kVUK Power Networks4.6 km33 MW9.9 MW
Verity Way Primary 11kVUK Power Networks6.4 km22 MW6.3 MW
West Letchworth Primary 11kVUK Power Networks7.4 km12 MW7.1 MW
Letchworth Grid 33kVUK Power Networks7.4 km94 MW19 MW
North Stevenage Primary 11kVUK Power Networks7.9 km23 MW9.7 MW

Thinking of connecting near Wymondley 2 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points