West Anglia Connection Node I 400kV substation: grid connection queue
West Anglia Connection Node I 400kV substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
3 projects with 2,340 MW are waiting to connect here (largest by capacity: mixed and other, solar + storage). Contracted dates run from 31 Oct 2034 to 30 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Melton Mowbray High Impact Energy Hub 1 | TELIS ENERGY UK LIMITED | Mixed and other | 1,000 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
| Melton Mowbray High Impact Energy Hub 2 | TELIS ENERGY UK LIMITED | Mixed and other | 1,000 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
| Melton Mowbray Solar | Cubico UK Development Limited | Solar + storage | 340 | 30 Oct 2037 | Low | 30 Oct 2037 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Sandy Primary 11kV | UK Power Networks | 3.3 km | 27 MW | 8.7 MW |
| Little Barford 11kV | UK Power Networks | 5.5 km | 37 MW | 7 MW |
| Little Barford 33kV | UK Power Networks | 5.5 km | 30 MW | 37 MW |
| Biggleswade Primary 11kV | UK Power Networks | 8.6 km | 17 MW | 2.3 MW |
| Edison Rd Grid 11kV | UK Power Networks | 9.8 km | 32 MW | 15 MW |
| Harrowden Primary 11kV | UK Power Networks | 12.7 km | 34 MW | 18 MW |
Thinking of connecting near West Anglia Connection Node I 400kV substation?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- West Anglia Connection Node D 400kV: 1,570 MW waiting
- Biggleswade 400kV: 3,056 MW waiting
- West Anglia Connection Node H 400kVSubstation: 2,000 MW waiting
- Grendon 400kV: 500 MW waiting
- Grendon 132kV: 41 MW waiting