West Anglia Connection Node D 400kV: grid connection queue
West Anglia Connection Node D 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
4 projects with 1,570 MW are waiting to connect here (largest by capacity: solar + storage, solar). Contracted dates run from 30 Oct 2030 to 31 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Cottered | LITTLETON PASTURES SOLAR LIMITED | Solar + storage | 600 | 30 Oct 2030 | Medium | 30 Oct 2030 | Scoping | none |
| Cottered - PVDP | SolarNine Ltd | Solar + storage | 520 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
| Noventum Cottered | NOVENTUM POWER SOLAR 5 LIMITED | Solar + storage | 210 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
| Huntington Solar PV | EDF ENERGY RENEWABLES LIMITED | Solar | 240 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Little Barford 11kV | UK Power Networks | 6.9 km | 37 MW | 7 MW |
| Little Barford 33kV | UK Power Networks | 6.9 km | 30 MW | 37 MW |
| Bourn Primary 11kV | UK Power Networks | 7.4 km | 17 MW | 9.6 MW |
| Croydon Primary 11kV | UK Power Networks | 8.3 km | 0.6 MW | 1.3 MW |
| Sandy Primary 11kV | UK Power Networks | 9.3 km | 27 MW | 8.7 MW |
| Cotton Primary 11kV | UK Power Networks | 9.7 km | 4.7 MW | 4.2 MW |
Thinking of connecting near West Anglia Connection Node D 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- West Anglia Connection Node I 400kV substation: 2,340 MW waiting
- WEST ANGLIA CONNECTION NODE B 400KV SUBSTATION: 1,250 MW waiting
- West Anglia Connection Node F 400kV: 3,429 MW waiting
- Biggleswade 400kV: 3,056 MW waiting
- Eaton Socon 400kV: 1,550 MW waiting