West Anglia Connection Node F 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

6 projects with 3,429 MW are waiting to connect here (largest by capacity: solar + storage, solar). Contracted dates run from 31 Oct 2034 to 31 Oct 2034.

6projects in the queue
3,429 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Little HarrowdenLittle Harrowden 10 Renewables LimitedSolar1,00031 Oct 2034Low31 Oct 2034Scoping1
Market Harborough Green Energy HubTELIS ENERGY UK LIMITEDMixed and other1,00031 Oct 2034Low31 Oct 2034Scoping1
Market HarboroughCONNECTID 1 LIMITEDSolar + storage70031 Oct 2034Low31 Oct 2034Awaiting Consentsnone
Noventum Market HarboroughNOVENTUM POWER SOLAR 1 LIMITEDSolar + storage24931 Oct 2034Low31 Oct 2034Scoping1
Lightsource BraybrookeLightsource Renewable UK Development LimitedSolar + storage24031 Oct 2034Low31 Oct 2034Scoping1
Nethercourt Solar & BESS FarmGreentech Invest UK (15) LimitedSolar + storage24031 Oct 2034Low31 Oct 2034Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Bourn Primary 11kVUK Power Networks2.2 km17 MW9.6 MW
Croydon Primary 11kVUK Power Networks8.4 km0.6 MW1.3 MW
Longstanton Primary 11kVUK Power Networks8.6 km22 MW8.4 MW
Hilton Primary 11kVUK Power Networks8.7 km1.7 MW1.7 MW
Madingley Rd Primary 11kVUK Power Networks8.8 km36 MW15 MW
Storeys Way Primary 11kVUK Power Networks10.1 km15 MW6.5 MW

Thinking of connecting near West Anglia Connection Node F 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points