Eaton Socon 400kV: grid connection queue
Eaton Socon 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
3 projects with 1,550 MW are waiting to connect here (largest by capacity: mixed and other, solar + storage). Contracted dates run from 31 Oct 2028 to 30 Oct 2033.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Eaton Socon Solar | BROCKWELL STORAGE & SOLAR LIMITED | Solar + storage | 500 | 31 Oct 2028 | High | 31 Oct 2030 | Scoping | none |
| Eaton Socon PV Storage | CSE37 Limited | Solar + storage | 50 | 30 Oct 2029 | Medium | 30 Oct 2029 | Scoping | none |
| Eaton Socon High Impact Green Energy Hub (HIGEH) 1 | TELIS ENERGY UK LIMITED | Mixed and other | 1,000 | 30 Oct 2033 | Low | 30 Oct 2033 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Offord Primary 11kV | UK Power Networks | 1.3 km | 11 MW | 9.3 MW |
| Cotton Primary 11kV | UK Power Networks | 3.1 km | 4.7 MW | 4.2 MW |
| Godmanchester Primary 11kV | UK Power Networks | 4.7 km | 2.8 MW | 4.2 MW |
| Huntingdon Grid 11kV | UK Power Networks | 6.2 km | 105 MW | 25 MW |
| Huntingdon Grid 33kV | UK Power Networks | 6.2 km | 62 MW | 51 MW |
| Perry Primary 11kV | UK Power Networks | 6.4 km | 10 MW | 4 MW |
Thinking of connecting near Eaton Socon 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- West Anglia Connection Node G 400kV: 1,920 MW waiting
- WEST ANGLIA CONNECTION NODE B 400KV SUBSTATION: 1,250 MW waiting
- West Anglia Connection Node C 400kV: 2,050 MW waiting
- West Anglia Connection Node A 400kV: 1,600 MW waiting
- West Anglia Connection Node H 400kVSubstation: 2,000 MW waiting