West Anglia Connection Node C 400kV: grid connection queue
West Anglia Connection Node C 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
3 projects with 2,050 MW are waiting to connect here (largest by capacity: battery storage, solar + storage). Contracted dates run from 31 Oct 2034 to 31 Oct 2034.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| NatPower Kinoulton Green Energy Park | DALBY ENERGY LIMITED | Battery storage | 1,330 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
| Noventum - Astwood | NOVENTUM POWER SOLAR 12 LIMITED | Solar + storage | 480 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
| Lightsource Grendon PV+BESS | Lightsource Renewable UK Development Limited | Solar + storage | 240 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 0 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 13 Oct 2026 | NatPower Kinoulton Green Energy Park | 31 Dec 2034 | 31 Oct 2034 | -2 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Huntingdon Grid 11kV | UK Power Networks | 4.5 km | 105 MW | 25 MW |
| Huntingdon Grid 33kV | UK Power Networks | 4.5 km | 62 MW | 51 MW |
| Woodwalton Primary 11kV | UK Power Networks | 4.8 km | 8.3 MW | 6.7 MW |
| Godmanchester Primary 11kV | UK Power Networks | 6.1 km | 2.8 MW | 4.2 MW |
| Offord Primary 11kV | UK Power Networks | 10.0 km | 11 MW | 9.3 MW |
| Bury Grid 11kV | UK Power Networks | 10.6 km | 17 MW | 16 MW |
Thinking of connecting near West Anglia Connection Node C 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- West Anglia Connection Node G 400kV: 1,920 MW waiting
- Eaton Socon 400kV: 1,550 MW waiting
- West Anglia Connection Node A 400kV: 1,600 MW waiting
- WEST ANGLIA CONNECTION NODE B 400KV SUBSTATION: 1,250 MW waiting
- Yaxley 400kV: 998 MW waiting