WEST ANGLIA CONNECTION NODE B 400KV SUBSTATION: grid connection queue
WEST ANGLIA CONNECTION NODE B 400KV SUBSTATION · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 1,250 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 30 Oct 2032 to 31 Oct 2034.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Wymondley Farm | Wymondley 10 Renewables Ltd | Solar + storage | 1,000 | 30 Oct 2032 | Low | 30 Oct 2032 | Scoping | none |
| Ashbrook Lane BESS | Downing Renewable Developments LLP | Battery storage | 250 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 13 Oct 2026 | Ashbrook Lane BESS | 31 Oct 2031 | 31 Oct 2034 | +36 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Hilton Primary 11kV | UK Power Networks | 0.7 km | 1.7 MW | 1.7 MW |
| Cotton Primary 11kV | UK Power Networks | 4.3 km | 4.7 MW | 4.2 MW |
| Offord Primary 11kV | UK Power Networks | 7.2 km | 11 MW | 9.3 MW |
| Bourn Primary 11kV | UK Power Networks | 7.5 km | 17 MW | 9.6 MW |
| Godmanchester Primary 11kV | UK Power Networks | 8.1 km | 2.8 MW | 4.2 MW |
| St Ives Primary 11kV | UK Power Networks | 9.2 km | 12 MW | 12 MW |
Thinking of connecting near WEST ANGLIA CONNECTION NODE B 400KV SUBSTATION?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Eaton Socon 400kV: 1,550 MW waiting
- West Anglia Connection Node A 400kV: 1,600 MW waiting
- West Anglia Connection Node F 400kV: 3,429 MW waiting
- West Anglia Connection Node D 400kV: 1,570 MW waiting
- West Anglia Connection Node E 400kV: 800 MW waiting